Brisbane 2032 · Project records

What changed?

Dated decisions, source revisions and new disclosures, in Brisbane time.

0 verified developments dated today

PEM-002 · Uniform Lot C

First recorded by QLD32. The buyer lists its status as “Closed”.

status
Unpublished → Closed
title
Unpublished → PEM-002 · Uniform Lot C
View official source ↗

PEM-002 · Uniform Lot B

First recorded by QLD32. The buyer lists its status as “Closed”.

status
Unpublished → Closed
title
Unpublished → PEM-002 · Uniform Lot B
View official source ↗

PEM-002 · Uniform Lot A

First recorded by QLD32. The buyer lists its status as “Closed”.

status
Unpublished → Closed
title
Unpublished → PEM-002 · Uniform Lot A
View official source ↗

PEM-002 · Uniform Lot D

First recorded by QLD32. The buyer lists its status as “Closed”.

status
Unpublished → Closed
title
Unpublished → PEM-002 · Uniform Lot D
View official source ↗

Cairns feedback reshapes grandstand design

More than 250 people and groups took part. Shade, drinking water and accessible routes were priorities. The current design provides weather protection for around 70% of permanent seats.

GIICA ↗ Barlow Park Stadium

Cairns Regional Council relocates services at Barlow Park

GIICA reported that council service relocations were underway ahead of the next early works package.

GIICA ↗ Barlow Park Stadium

Main construction in Cairns expected from mid-2027

GIICA expects grandstand demolition and site preparation to follow council service relocations.

GIICA ↗ Barlow Park Stadium

Moreton Bay inclusion coach reaches 181 organisations

In its first year, the council’s Sport4All coach worked with 181 organisations during 2026 to help people with disabilities take part in community sport. Council identified inclusion in local sport as a priority ahead of Brisbane 2032.

City of Moreton Bay ↗

IOC moves sports programme decision to April 2027

The IOC now plans to settle the Olympic programme at its 147th Session in Punta Cana. It expects an interim review of disciplines in December 2026.

International Olympic Committee ↗

Darumbal representatives discuss planning on the Fitzroy River

GIICA published perspectives from two Darumbal People Aboriginal Corporation directors on the river’s cultural significance as planning continues.

GIICA ↗ Rockhampton Flatwater Facility

BESIX Watpac and John Holland advance in stadium selection

The joint venture moved to the next stage of early contractor involvement. GIICA expected the selection process to finish in the new year.

GIICA ↗ Brisbane Stadium

Main stadium construction expected in 2027

GIICA connected the start of main construction with completion of its builder selection process.

GIICA ↗ Brisbane Stadium

Organising Committee reports a $23.099 million operating loss

The loss is the difference between $29.181 million of annual expenses and $6.082 million of income. A budget overrun requires a comparison with the approved budget for the same period and scope.

Brisbane 2032 Organising Committee via Queensland Parliament ↗

GIICA recognised $89.124 million of expenses in 2025–26

The authority-wide figure includes $69.624 million for supplies and services and $16.829 million for employees. The reporting period ended on 30 June 2026.

State of Queensland (GIICA) ↗

Centenary Pool handed to GIICA

GIICA confirmed that it took possession on the announced date and began preparing the site.

GIICA ↗ National Aquatic Centre

Centenary Pool closes to the public

The pool closed the day before GIICA took possession. Its 1 September update said part of the Spring Hill side of the park remained accessible.

GIICA ↗ National Aquatic Centre

Up to $1.2 billion in Commonwealth funding allocated to the stadium

The funding agreement places a cap on the Commonwealth stadium allocation. The venue’s total cost is a separate figure.

Federal Financial Relations ↗ Brisbane Stadium

Barlow Park Stadium practical completion reporting window

The funding schedule gives Q2 2030 as the approximate quarter to report practical completion. The public agreement does not specify an opening day.

Federal Financial Relations ↗ Barlow Park Stadium

Sunshine Coast Stadium practical completion reporting window

The funding schedule gives Q2 2030 as the approximate quarter to report practical completion. The public agreement does not specify an opening day.

Federal Financial Relations ↗ Sunshine Coast Stadium

Logan Indoor Sports Centre practical completion reporting window

The funding schedule gives Q4 2030 as the approximate quarter to report practical completion. The public agreement does not specify an opening day.

Federal Financial Relations ↗ Logan Indoor Sports Centre

Redland Whitewater Centre practical completion reporting window

The funding schedule gives Q4 2030 as the approximate quarter to report practical completion. The public agreement does not specify an opening day.

Federal Financial Relations ↗ Redland Whitewater Centre

Queensland plans around 1,800 homes at the Showgrounds

The government’s plan converts the village precinct to housing after the Games. Early work on site includes restoration of heritage grandstands.

Queensland Government ↗ Brisbane Athlete Village

National Aquatic Centre design team selected

ARM and NH Architecture partnered with Arkhefield. GIICA lists ARM Joint Venture as the legal supplier of architectural services.

Queensland Government ↗ National Aquatic Centre

BMD appointed for stadium early works

GIICA identified BMD as the early works contractor. Its disclosure lists GF26/137 for the same supplier and scope at $51.1 million including GST.

GIICA ↗ Brisbane Stadium

Stadium early works package expected to finish in mid-2027

BMD’s package includes earthmoving, haul roads, drainage and retaining walls. The target covers early works only.

GIICA ↗ Brisbane Stadium

Queensland budgets $417 million for venue delivery in 2026–27

This is one financial year’s provision for GIICA’s venue work within the $7.1 billion programme. Actual spending is reported separately.

Queensland Treasury ↗

Budget sets a $3.5 billion envelope for the athlete villages

The state budget covers athlete accommodation at four locations in partnership with the private sector. The published figure gives the size of the programme across years.

Queensland Treasury ↗

Queensland forecasts $348 million for athlete villages in 2026–27

The forecast sits within the $3.5 billion athlete village envelope. The budget does not split the annual forecast by village.

Queensland Treasury ↗

Stage 1 of The Wave has a $5.5 billion investment

The Commonwealth and state fund the Beerwah–Caloundra section. It includes the previously announced $2.75 billion Commonwealth commitment. The state budget provides $460 million for this stage in 2026–27.

Queensland Treasury ↗ The Wave · rail stages 1 and 2

Logan and Gold Coast Faster Rail has a $5.75 billion estimate

The state budget identifies the corridor as supporting the Games and provides $651 million for 2026–27. The project will also serve everyday passengers.

Queensland Treasury ↗ Logan and Gold Coast Faster Rail

Initial site works begin at Victoria Park

GIICA took possession of the Herston side and began preparing the stadium site.

GIICA ↗ Brisbane Stadium

Herston park entrances and road access change

Gilchrist Avenue closed to public vehicles. Access into the work area from the Herston and Kelvin Grove busway stations closed, and the North Brisbane Bikeway route changed.

GIICA ↗ Brisbane Stadium

Commonwealth EPBC referral decision issued

GIICA recorded a ‘not a controlled action’ decision for the Victoria Park referral. This is the decision under the federal EPBC process.

GIICA ↗ Brisbane Stadium · National Aquatic Centre

GIICA expects Victoria Park early works by mid-year

GIICA identified initial works at Victoria Park as one of the next venue milestones.

GIICA ↗ Brisbane Stadium

Populous to design the Petrie indoor sports centre

GIICA appointed Populous as principal architect. The announcement does not specify this project’s design fee.

GIICA ↗ Moreton Bay Indoor Sports Centre

Stadium principal architects appointed

COX, Hassell and Azusa Sekkei make up the design team. GIICA lists COX and Hassell as the contracted supplier for the design-services award.

GIICA ↗ Brisbane Stadium

Queensland’s share of the venue program

The Queensland Audit Office recorded the state's $3.665 billion contribution. This amount is part of the joint program allocation.

Queensland Audit Office ↗

Unite32 appointed as the venue program delivery partner

Laing O’Rourke and AECOM lead the team supporting GIICA across 17 venues. The announcement gives no contract price.

Queensland Government ↗

Cross River Rail’s first passenger services moved from 2026 to 2029

The Queensland Audit Office documented the revised first-service target after major contract negotiations. The later whole-programme estimate also includes associated works and future operations and maintenance.

Queensland Audit Office ↗ Cross River Rail

Cross River Rail’s capital budget increased by a further $170 million

The September 2024 revision funded tunnel and station works pending completion of contract negotiations. The later whole-programme estimate also includes associated works and costs for future operations. It measures a broader scope.

Queensland Audit Office ↗ Cross River Rail

IOC initially plans sports programme decision in 2026

The IOC reaffirmed its earlier timetable after adding a review of disciplines.

International Olympic Committee ↗

Governments agree to a $7.1 billion venue program

The Australian and Queensland governments committed funding for 17 new or upgraded venues.

Australian Government ↗

Commonwealth contribution capped at $3.435 billion

This contribution sits within the $7.1 billion program allocation.

Australian Government ↗

The original bid estimated Games operations at $4.9 billion in 2021 dollars

The audit gives the same estimate as $5.9 billion in 2032 dollars. The bid included temporary venue infrastructure and assumed income from the IOC, sponsorships and ticketing. Permanent venues have their own budget.

Queensland Audit Office ↗

Cross River Rail’s capital budget rose by $960 million

The audit records a March 2023 increase for the rail project as materials and supply costs rose. The comparison covers the core project budget, including private financing.

Queensland Audit Office ↗ Cross River Rail